Project Time Line
Start-stop dates for each of the project's main line contracts
Cheltenham Avenue to Route 73/Church Road (Section 102)
- Start Major Construction: March 2005
- Complete Major Construction: November 2008
Route 73/Church Road to Highland Avenue (Section 100)
- Start Major Construction: February 2004
- Complete Major Construction: November 2006
Fort Washington/PA Turnpike Interchange (Section 103)
- Start Major Construction: January 2005
- Complete Major Construction: November 2008
Highland Avenue to Route 63/Welsh Road (Section 101)
- Start Major Construction: July 2007
- Complete Major Construction (est.) : Fall 2010